Topic #1
Request to address drainage at newly bitumised Ferguson Hall carpark which is channeling water under the building.
Outcome
Inspection carried out 12/04/2023. Operations to action a solution.
Date Completed
In progress.
Topic #2
Request to remove lock on dump point.
Outcome
Advocate contacted by Senior Project Officer to discuss and lock removed with cleaner to monitor.
Date Completed
17/03/2023
Topic #3
Request to improve use of Dardanup Library by community.
Outcome
Manager Community Development contacted advocate via email outlining upcoming events at Dardanup Library plus addition to mailing list for regular updates.
Date Completed
20/02/2023
Topic #4
Request to action linemarking on Wellington Mills Road due to perceived safety hazard.
Outcome
Request sent to Main Roads WA. Traffic counter installed 12/05/2023 to assess traffic volumes before progressing further.
Date Completed
In progress.
Topic #5
Query regarding potential subdivision of Henty property.
Outcome
Advocate contacted by Senior Planning Officer via email with outline of Local Planning Scheme guidelines indicating if an application was received support would not be recommended by the Shire however final decision rests with WA Planning Commission.
Date Completed
27/02/2023
Topic #6
Query regarding possible removal of single tree in SCA2 Henty location.
Outcome
Advocate contacted by Senior Planning Officer via email outlining criteria for removal of tree without development approval.
Date Completed
27/02/2023